The decommissioning of the Old Dominion facility in Colorado was executed as a comprehensive, multi-phase project focused on the safe removal, recycling, and compliance documentation of all power, cooling, and electrical infrastructure. Trash Masters LLC’s role was to provide a full-service, environmentally responsible dismantling and removal process — covering generators, UPS systems, CRAC units, chillers, PDUs, racks, and fire suppression equipment.
Phase 1: Power Systems Removal
1. Generator & Associated Equipment
- Removal of one 2015 Cummins QST30-G5NR2 1000 kW generator (Cummins DQFAD package, 189 hours).
- Disconnection and cutting of electrical feeds near flush with concrete pad, capped with weather-tight PVC fittings.
- All fuel drained, electrical conduits disconnected, and crane rigging coordinated for transport.
- Filing of paperwork with the State of Denver and coordination with the local Fire Marshall for AST closure.
- Concrete pad left in place (integrated with adjacent pad).
2. Uninterruptible Power Supplies (UPS)
- Removal of two Eaton 9395-275 kVA UPS systems with battery cabinets.
- Complete disconnection from ATS and PDUs, safe electrical termination, and forklift removal.
- Housekeeping pads left in place per client request.
3. Battery Removal and Recycling
- Removal of 160 SLA CSB HR/HRL-Series batteries (non-hazardous).
- Electrical disconnection, palletization, and forklift removal.
- Certified recycling documentation provided upon request.
Phase 2: Cooling Systems Decommission
1. Computer Room Air Conditioning (CRAC) Units
- Removal of (2) Opticool RPW floor units, (4) Opticool ceiling-mounted units (R-134A), and (1) MovinCool Classic Plus 14 portable unit.
- All refrigerant lines cut near flush with pads and sealed with PVC caps.
- Masonry and drywall repairs performed where refrigerant lines were removed.
- Draining of refrigerants, conduit disconnection, and removal of piping.
- Nortec humidifiers excluded from scope.
2. Chillers
- Removal of two Carrier 30RAP0606DAG chillers (410A refrigerant).
- All refrigerant and water drained; electrical and piping systems disconnected.
- Concrete pad demo excluded but can be added if directed.
- Pads left intact and capped weather-tight.
Phase 3: Electrical & Rack Infrastructure
1. Power Distribution and Electrical Equipment
- Removal of (2) Eaton B PDUs, (4) Starline Bus Ducts, (2) GE SB UOUT1-2 panels, (2) GE PB MECHA.B panels, (2) GE SB MDP panels, and (1) ATS section.
- All feeds cut near flush at pad level and capped with weather-tight PVC fittings.
- Electrical disconnections performed by licensed Colorado electricians.
- Concrete pads left in place unless otherwise directed.
- Two electrical troughs not in scope.
2. Server Rack Removal
- Removal of 24 Opticool door racks with Eaton enclosures.
- Network and power cabling disconnected; racks loaded for shipment or recycling.

Phase 4: Fire Suppression & Safety Systems
1. Fire Suppression (FM-200 System)
- Removal of three Fike FM-200 cylinders (928 lbs total) and all associated piping and nozzles.
- Fire alarm system reprogrammed to remove dependency on gas suppression.
- Sprinkler system modifications excluded.
2. VESDA System
- Removal of one dual-panel VESDA system including electrical disconnect and alarm reprogramming.
- No modification to other smoke detection devices.
Phase 5: Final Area Cleanout
Rooms and Spaces
- Full cleaning and removal of debris from MDF/Electrical/Cooling/Server Room complex.
- Outdoor equipment yard cleaned (housing ATS, chillers, and generator).
- All spaces broom-swept and left clean.
Key Outcomes
- Complete mechanical and electrical decommission of power and cooling systems.
- Certified recycling and environmental documentation for batteries and refrigerants.
- Coordination with local Fire Marshall and state agencies for AST closure.
- Site left safe, clean, and ready for landlord inspection or redevelopment.